Å·ÃÀAƬ

How ETAP Microgrid optimized a 100% renewable power supply in the Tabuk region on the Red Sea

Off-grid microgrids supplied by renewables typically have batteries and are very sophisticated. Simulating and having a digital twin of the entire microgrid is essential to designing, selecting the control scheme, and setting the optimal control settings.
by Mohammad Zadeh, Chief Product Officer, SVP of Engineering, ETAP

The Red Sea development in northwest Saudi Arabia includes several permanently isolated microgrids powered primarily by solar PV and battery energy storage systems (BESS). Each microgrid must operate reliably with zero grid connection, maintain stability under rapidly changing renewable conditions, and withstand N-1 contingencies - all while keeping diesel generators offline except in emergency conditions. To meet these challenges, ETAP Microgridâ„¢ Control provides advanced primary and secondary controls, coordinated asset dispatch, and full digital twin validation.


Microgrid control with 100% renewable power supply

Challenges

1. Managing a microgrid supplied almost entirely by solar PV and batteries

PV is grid-following, while the BESS must act as the grid-forming anchor that maintains system stability. Coordinating both assets to keep the system in balance is complex.

2. Ensuring frequency stability under changing solar and load conditions

Because both PV and BESS operate in droop mode, frequency naturally deviates from nominal, unless a secondary control mechanism restores it.

3. Voltage regulation with multiple distributed DERs

Both PV, BESS, and generators share reactive power through QV droop and require a supervisory secondary voltage controller.

4. Handling renewable variability

During sunny days, PV exceeds load and charges the BESS, and during cloudy or winter days batteries must support the full load for extended periods.

5. Executing reliable black start without damaging transformers

Soft energization must avoid inrush currents of 6 - 7 p.u., which solar and BESS cannot tolerate without advanced control.

Which solutions did they choose?

Selected applications

ETAP Microgrid

  • Optimized design and validation of DERS
  • Black start & soft energization analysis
  • Controller hardware and equivalent simulation modeling
  • Load vs. generation capacity balancing

ETAP Digital Twin

  • To build and analyze a virtual representation of the electrical network, including BESS and renewable power sources.

Why do they use ETAP?

Main customer benefits

Complete digital twin of the microgrid. The entire microgrid - including PV, BESS, ICE generators, loads, and controls - can be simulated end-to-end before commissioning.

Coordinated primary & secondary controls. ETAP ensures stable frequency and voltage even under rapid renewable fluctuations and N-1 contingencies.

Optimization of curtailment & reserve margins. BESS reserve can be managed dynamically while PV curtails or ramps according to the microgrid controller logic.

Reliable black start under demanding conditions. Soft energization prevents damaging inrush currents and ensures safe restoration of service.

Reduced field testing (HIL) and commissioning risks. Validation of the entire control logic in ETAP minimizes on-site trial and error, reducing cost and time.

 

Conclusion

This Red Sea microgrid project demonstrate how ETAP enables fully renewable, off-grid power systems to operate reliably and safely. Through advanced control algorithms, the coordination of all elements of the systme, including PV, BESS generators, and secondary control layers, within an intelligent single line diagram enables  detailed digital twin validation. ETAP ensures that microgrids with extreme renewable penetration remain stable - even under contingencies, load variations, and black start scenarios.

What do they think about ETAP?

Perspectives

One of the beauties of using ETAP is that now that we have the complete digital twin of the system, not only can we set these Microgrid Controller black start set points in ETAP, but we can also see the entire interaction of the controller black start function in simulation including the primary controllers.
by Mohammad Zadeh, Chief Product Officer, SVP of Engineering, ETAP



Videos

The Red Sea Utility Grid is in the Tabuk province of Saudi Arabia. The site is a vast 33,000 km2 of islands, lagoon, coastal plain and mountains with extremely diverse marine life and terrestrial landforms. The grid is divided into four off-grid microgrids. The focus of this presentation is about three of the microgrids that are very similar in size and operation. Each of these microgrids includes two PV generation (total 6 MW), two battery storages (total 5MW, ~18 MWh), and two emergency backup diesel generators (~ total 3.8 MW). The system is designed to achieve high reliability by having redundancy at various levels.


Å·ÃÀAƬ


Packages/Products