Top Products
The Red Sea development in northwest Saudi Arabia includes several permanently isolated microgrids powered primarily by solar PV and battery energy storage systems (BESS). Each microgrid must operate reliably with zero grid connection, maintain stability under rapidly changing renewable conditions, and withstand N-1 contingencies - all while keeping diesel generators offline except in emergency conditions. To meet these challenges, ETAP Microgridâ„¢ Control provides advanced primary and secondary controls, coordinated asset dispatch, and full digital twin validation.
Shandong Electric Power Construction Corporation III, or SEPCO III, was founded in 1985 and is an A-level subsidiary of POWERCHINA. It is a comprehensive construction group involved in the engineering and development of various types of projects in many countries around the world, such as power stations, seawater desalination, infrastructure and other engineering construction projects. SEPCOIII uses the EPC method (Engineering, Procurement, Construction) on many of their projects to provide their customers with precision project research, design, construction, operation and maintenance.
Location: Tabuk, Saudi Arabia
Year: 2023
Microgrid control with 100% renewable power supply
1. Managing a microgrid supplied almost entirely by solar PV and batteries
PV is grid-following, while the BESS must act as the grid-forming anchor that maintains system stability. Coordinating both assets to keep the system in balance is complex.
2. Ensuring frequency stability under changing solar and load conditions
Because both PV and BESS operate in droop mode, frequency naturally deviates from nominal, unless a secondary control mechanism restores it.
3. Voltage regulation with multiple distributed DERs
Both PV, BESS, and generators share reactive power through QV droop and require a supervisory secondary voltage controller.
4. Handling renewable variability
During sunny days, PV exceeds load and charges the BESS, and during cloudy or winter days batteries must support the full load for extended periods.
5. Executing reliable black start without damaging transformers
Which solutions did they choose?
ETAP Microgrid
ETAP Digital Twin
Why do they use ETAP?
Complete digital twin of the microgrid. The entire microgrid - including PV, BESS, ICE generators, loads, and controls - can be simulated end-to-end before commissioning.
Coordinated primary & secondary controls. ETAP ensures stable frequency and voltage even under rapid renewable fluctuations and N-1 contingencies.
Optimization of curtailment & reserve margins. BESS reserve can be managed dynamically while PV curtails or ramps according to the microgrid controller logic.
Reliable black start under demanding conditions. Soft energization prevents damaging inrush currents and ensures safe restoration of service.
Reduced field testing (HIL) and commissioning risks. Validation of the entire control logic in ETAP minimizes on-site trial and error, reducing cost and time.
This Red Sea microgrid project demonstrate how ETAP enables fully renewable, off-grid power systems to operate reliably and safely. Through advanced control algorithms, the coordination of all elements of the systme, including PV, BESS generators, and secondary control layers, within an intelligent single line diagram enables detailed digital twin validation. ETAP ensures that microgrids with extreme renewable penetration remain stable - even under contingencies, load variations, and black start scenarios.
What do they think about ETAP?
One of the beauties of using ETAP is that now that we have the complete digital twin of the system, not only can we set these Microgrid Controller black start set points in ETAP, but we can also see the entire interaction of the controller black start function in simulation including the primary controllers.by Mohammad Zadeh, Chief Product Officer, SVP of Engineering, ETAP
The Red Sea Utility Grid is in the Tabuk province of Saudi Arabia. The site is a vast 33,000 km2 of islands, lagoon, coastal plain and mountains with extremely diverse marine life and terrestrial landforms. The grid is divided into four off-grid microgrids. The focus of this presentation is about three of the microgrids that are very similar in size and operation. Each of these microgrids includes two PV generation (total 6 MW), two battery storages (total 5MW, ~18 MWh), and two emergency backup diesel generators (~ total 3.8 MW). The system is designed to achieve high reliability by having redundancy at various levels.
Microgrid
Grid Modeling & Visualization